St Helena Airport features a common building for airport operations support. Image courtesy of SHG Access Office.
The passenger terminal building at St Helena Airport features a glass facade. Image courtesy of SHG Access Office.
The airport runway has a landing distance (LDA) of 1,550m. Image courtesy of Remi Bruneton.
The air control tower (ATC) operations are controlled by Basil Read in partnership with Lanseria Airport. Image courtesy of SHG Access Office.
The terminal building features various security facilities. Image courtesy of SHG Access Office.
一个新的码头规划d at the Rupert's valley for loading and unloading goods. Image courtesy of Remi Bruneton.

St Helena Int. Airport

Saint Helena International Airport is a green field airport constructed in the British Overseas Territory of Saint Helena in the South Atlantic Ocean.

The airport is owned by the Saint Helena Government (SHG) and operated by Basil Read in partnership withLanseria Airportas part of a ten year contract.

The new airport project was approved by the UK Government in 2011. Construction started in 2012 and the airport was opened in 2016. The Saint Helena airport welcomed its first scheduled commercial flight in October 2017.

Travel to the island from Cape Town, South Africa, would take seven days on the RMS St Helena, the only means of travel to and from the island. The airport significantly reduces travel time from Cape Town to five hours.

In addition to providing air access, the airport also addresses some of the socio-economic problems of St Helena and makes it financially independent.

The airport has been assigned ‘HLE’ by the International Air Transport Association (IATA) and ‘FHSH’ by the International Civil Aviation Organisation (ICAO).

St Helena airport facilities

The new airport features two main buildings, namely a passenger terminal building and a combined building, as well as a number of smaller ancillary buildings.

The combined building was the first facility constructed at the airport. It houses a number of auxiliary functions required for the airport operations, includingair traffic control, rescue and firefighting services, and a meteorological office.

Construction of the 2,500m² terminal building started in June 2014.

The ancillary buildings include a generator compound, an access control building and a storage compound.

The project also included the construction of a 14km access road connecting the airport to the Rupert’s valley, a new waterfront in Rupert’s, a bulk fuel installation in the valley and an inshore sea rescue facility.

Runway and aprons

St Helena Airport features a 1.95km-long concrete runway, designated 20/02. It has a landing distance (LDA) of 1.55km, take-off run available (TORA) of 1.85km, take-off distance available (TODA) of 2,775m and accelerate stop distance available (ASDA) of 1.85km.

The runway is capable of accommodating Code C aircraft such as the Boeing 737-700 or Airbus 319. It is accompanied by aprons for two aircraft, taxiways, and a bulk fuel installation for six litres of diesel and aviation fuel.

Contractors involved

South African construction firm Basil Read has been appointed as thedesign build and operate (DBO)contractor for the airport in November 2011.

The DBO contract involved a design and build phase of four years, and enables the company to handle the airport operations in partnership with Lanseria Airport for a period of ten years.

The scope of the DBO contract included construction of the entire airport infrastructure and facilities. During the operations phase, the company will provide all the required services such as air traffic control, and training and deployment of firemen.

All the raw material required for the airport construction was transferred to the island on a 2,500t ship specially chartered by Basil. The company also constructed berthing and uploading facilities to facilitate the same. It employed more than 600 people during the construction phase, while more than 100 off-island personnel were involved in logistics, design and support functions.

“The airport will also address some of the socio-economic problems of St Helena and make it financially independent.”

Other contractors involved with the project include Halcrow, which offered project management services, and Penspen, the fuel management contractor for managing bulk fuel installation and airport fuel facility (AFF). South Africa-based KMH Architects designed the terminal building and other facilities for the project.

South African aviation and travel company Comair offers air services at the airport. The airline provides services from the island to regional and international destinations, including London, Paris, Frankfurt, New York, Buenos Aires, Dubai, Hong Kong and Sydney, as well as connections through Johannesburg.

Financing

The total investment required for the project was £250m ($363.76m), which includes £201.5m for design and construction, up to £35.1m for the ten-year operation, and £10m for shared risk contingency.

Funded by the UK Department for International Development (DFID), the project is the biggest single investment made by the government in St Helena Island.

Parking at St Helena airport

A facility with designated parking spaces for private vehicles, motorcycles, buses and taxis is located outside the terminal building. The facility also provides disabled-access parking.

Related Projects